“Hidden Hazards During The Shift”
A crew is supposed to complete safety-sensitive procedures in one shift. But the crew doesn’t finish in time. They must pass on the work – right in the middle of things – to another crew.
Most organizations provide communications protocols so the second crew knows what safety procedures remain undone. But protocols aren’t always enough. Here’s a case that shows how a company that engaged in rigorous safety planning, including communications, still failed to prevent an accident.
A valve-replacement project required two shifts of work. The night shift was tasked with draining pressurized steam piping from the system; the day shift was tasked with replacing a leaky valve once the system was fully drained.
The night shift was unable to complete the drainage job during its shift. When the night-shift supervisor turned over the project checklist to the day-shift supervisor, he highlighted about two dozen procedures that had been completed.
Only four more valves needed to be opened and drained. Problem was two of these valves were the last two items on the checklist.
The other two were near the top of the checklist – with a handwritten note next to them saying these two valves needed to be opened.
The night-shift supervisor also verbally communicated to the day-shift supervisor about all four valves during the shift handoff.
Later, the day-shift supervisor forgot about the night supervisor’s warning and overlooked the handwritten notes on the checklist. He only instructed his crew to drain two valves, not four – which would leave the line pressurized.
Add inexperience …
There were still two more chances to catch the error, though. First, the workers could have noticed that when the two valves were opened, no steam came out.
But an inexperienced worker was given the task. He didn’t see the lack of steam as a warning sign.
Second, the day supervisor checked the open valves, saw no steam coming out and assumed the system had been fully drained.
He issued a permit for a contractor to replace the leaky valve.
So the crew missed both opportunities. A contract worker cracked open the seal on the leaky valve, and he and two other workers were engulfed in pressurized steam.
One worker spent six weeks in the hospital with burns over 60% of his body.
We can see how tricky these types of accidents are. Everybody thought they were following the right protocols, but communication broke down anyway.
The mistakes started with the handoff and were compounded by a novice worker who didn’t notice the signs of a problem and a supervisor who didn’t debrief the worker.
“There are seven things that will destroy us: Wealth without work; Pleasure without conscience; Knowledge without character; Religion without sacrifice; Politics without principle; Science without humanity; Business without ethics.” — Mahatma Gandhi
Thanks for the share, TO!
“I could only achieve success in my life through self-discipline, and I applied it until…
Alabama Mine Expansion Could Test Biden Policy on Private Extraction of Publicly Owned Coal Click…
A former Utah coal town could soon become a hub for low-carbon cement Siga by…
Safety Health Talks- Winter Walking Click here for the pdf of this important health talk…
This website uses cookies.